St Sava College

WELCOME TO THE ST. SAVA COLLEGE WEBSITE

 


DECEMBER 2015 - CURRENT WORK

29November2015small

SURFACE DRAINAGE: Work is approaching completion with only a few pits to be finished. This has been a huge job.
SEWERAGE LINES: Work is progressing well with more than 150 metres of trenching completed and pipe laid. After running of electrical conduit over the next week all trenches will be backfilled.
SEWERAGE SYSTEM: Secondary sewerage tank delivered and installed and absorption trenching complete.
WATER: Running of hot, cold and tank water lines to all wet areas

 

WORKS IN PLANNING
CLADDING: Cladding and fascia work to external areas
RENDERING: of existing blockwork
ELECTRICAL:
preliminary design
MECHANICAL: preliminary design

 

SPECIAL THANKS:
Andrej
Branislav
Janko
Milan
Radovan
Milan Bajic
Ozren Coso
Dusan Cupic
Nenad Djogo
Dragan Djordjevic
Surveyor Dragan
Brane Gligoric
Dragan Ignjic
Bogdan Komatovic
Milos Komatovic
Bogomir Kuliza
Bobi Oliveric
Milan Pantelic
Miljan Pavlovic
Dejan Polumirac
Neven Pupovac
Fr Sasa Radoicic
Biljan Stankovic
Predrag Stankovic
Dragan Stegnjaic
Stevo Trifunovic
Miroslav Uzelac
Vele Kovacevic
Zoran Cupac
Fr Djuro Djurdjevic
Danny Jovanovic
Miroljub Mihaijlovic
Randon Ilic
St George Cabrammatta

 


 

NEWS:

  • Progress Report Novemeber 2015

    We have received some glazing quotes and have met some contractors on site to discuss the details. We will need about $150,000+ for all glazing so at present we are looking for a sponsor for this work.
    We have also started discussions about internal works, especially electrical and mechanical design, rendering and cladding. If anyone can help with rendering and cladding/gyprocking let us know.

  • Progress Report October 2015

    Dragan Stegnjaic and his team of volunteers have been hard at work digging trenches for surface drainage lines and also building block work pits for access to the lines.
    They have also started digging trenching for the sewerage system and we expect to have one of the sewerage tanks installed in the next few weeks. We will then have some more digging for the absorption trench for the sewer as well.

  • Progress Report September 2015

    Dragan Stegnjaic has commenced running some main water lines into the college building and later we will need to continue the lines into all the bathrooms and the kitchen.
    Earthworks for surface drainage is continuing with excavators hard at work, and pipes, and block work being laid. We are only working on Saturdays but a lot can be done with more hands.
    If you can help please contact us.

  • Progress Report August 2015

    We have priced our sewerage system and will be purchasing it in stages. Priority has been given to excavation and drainage works at present.
    We have also finalised our list of bathroom fittings and are looking for sponsors for the fittings. Price will be about $20,000 for all bathrooms.
    We continue with excavation works for surface drainage. Some of the pits will be very deep and there are many hours of work needed to complete this important job.